Mimosa Bridge Nears Completion

Sources

  • Cầu cạn đèo Mimosa ở cửa ngõ Đà Lạt thi công thần tốc sau sạt lở — Thanh Niên

Technical Details

In a remarkable display of thần tốc (rapid) construction, the Mimosa bridge in Đà Lạt is nearing completion, with reportedly 80% of the work finished in just 50 days.

According to sources, the bridge's construction was expedited after a sạt lở (landslide) occurred in the area, causing concerns about traffic safety. As a local, it's heartening to see the swift progress on this critical infrastructure project, which will undoubtedly improve the daily commute for residents and visitors alike. The bridge, located at Km226+600 - Km226+800 on Quốc lộ 20, is expected to be fully operational by the end of 2025.

As Ông Bùi Huy Khoa, Director of Công ty Tiến Thành, noted, the company has been working tirelessly to complete the project. This new bridge will not only enhance the beauty of our city but also provide a safer and more convenient travel experience for everyone. As we look forward to the bridge's completion, we can't help but feel a sense of pride and excitement for the future of our beloved Đà Lạt.

Mimosa Bridge Construction Update

  • Location: Km226+600 - Km226+800, Quốc lộ 20, Đà Lạt
  • Construction progress: 80% complete in 50 days
  • Expected completion date: End of 2025
  • Contractor: Công ty Tiến Thành The Mimosa bridge is a critical infrastructure project aimed at improving traffic safety and reducing congestion in the area. With its completion, residents and visitors can expect a smoother and more convenient travel experience.