Xuan Huong Lake Road Delayed

Sources

  • Đường nối hồ Xuân Hương ở Đà Lạt chưa hẹn ngày về đích — Thanh Niên

Technical Details

In a recent update, the Da Lat Management Board revealed that the road connecting Xuan Huong Lake, a beloved landmark in our city, is still facing delays.

According to Thanh Nien, the project, which was supposed to be completed by 2026, has only achieved 16.8% of its goal, with over 3.16 trillion VND already spent. As a local, it's disheartening to see this project, which aims to improve the traffic flow around the lake, still pending. The road, which stretches from Lu Gia Street to Xuan Huong Lake, is a crucial part of our city's infrastructure.

However, with 11 households yet to hand over their land, the construction process is at a standstill. As Ban Quan ly du an dau tu xay dung khu vuc Da Lat noted, the project's delay is not only affecting the traffic but also the overall development of our city.

As we wait for the project's completion, we can't help but think about the potential benefits it will bring to our community, from improved traffic flow to enhanced scenery around the lake. For now, we'll have to be patient and hope that the project will be back on track soon.

Project Details

  • Total investment: 18.78 trillion VND
  • Completed investment: 3.16 trillion VND
  • Progress: 16.8%

Reasons for Delay

  • Land handover issues: 11 households yet to hand over their land
  • Construction challenges: complex terrain and limited access to the area

Impact on the Community

  • Traffic congestion: the delayed project is affecting the traffic flow around Xuan Huong Lake
  • Economic impact: the project's delay is also affecting the local economy, with businesses and residents waiting for the improved infrastructure