国道28B号の改良工事に遅れ

原文を表示
Delays on Quốc Lộ 28B Upgrade Frustration Mounts as Quốc Lộ 28B Upgrade Faces Delays. As a crucial route connecting Đà Lạt to Phan Thiết, the upgrade of Quốc Lộ 28B has been a long-awaited project for locals and travelers alike. However, **according to Tuổi Trẻ**, despite nearing completion, certain sections of the road remain unfinished, causing frustration for commuters. One such section is at Km21, where the road is still littered with dirt and rocks, forcing vehicles to slow down. **Anh Nguyễn Quốc Phong**, a regular user of the road, expressed his disappointment at the slow progress, citing that other more complex sections have been completed much sooner. The delay is attributed to the discovery of hard rock during excavation, which has damaged machinery and hindered the construction process. **Lê Văn Chung**, Deputy Director of the Central Region Road Project Management Board, assures that additional machinery has been brought in to expedite the process, with a projected completion date by the end of June. As the road is a vital link between Đà Lạt and the coastal town of Phan Thiết, its upgrade is eagerly anticipated by the local community. With the onset of the rainy season, concerns about landslides and road safety are heightened, especially in areas like đèo Đại Ninh. The community looks forward to the timely completion of this project, which will not only improve connectivity but also enhance the safety and convenience of travel for all who use this essential route. ## Quốc Lộ 28B Upgrade Details. The project aims to upgrade a 68km stretch of Quốc Lộ 28B, connecting Bình Thuận and Lâm Đồng, with a total investment of over 1,400 billion đồng. The construction is divided into packages, with the segment at Km21 being part of package XD01, handled by Công ty TNHH xây dựng Thành Phát. **Key Facts:*** Total length: 68km* Total investment: Over 1,400 billion đồng* Project timeline: Initially planned for completion, but facing delays* Notable challenges: Hard rock excavation, machinery damage, and landslide risks. The upgrade of Quốc Lộ 28B is a significant infrastructure project for the region, expected to improve road safety, reduce travel times, and boost local economic development.

出典

  • Dự án nâng cấp quốc lộ 28B: Vẫn còn những đoạn thi công ngổn ngang — Tuổi Trẻ

Technical Details

国道28B号の改良工事が遅延、不満が高まる。

ダラットとファンティエットを結ぶ重要な道路である国道28B号の改良工事は、地元住民や旅行者が長年待ち望んできた事業です。しかし、Tuổi Trẻ紙によると、完成が近づいているにもかかわらず、一部の区間では工事が終わっておらず、日々この道路を利用する人々の不満を招いています。その一つがKm21地点で、道路にはいまだに土砂や岩石が散乱し、車両は減速を余儀なくされています。

この道路を日常的に利用するNguyễn Quốc Phong氏は、より複雑な他の区間がはるかに早く完成したことを挙げ、工事の進み具合に失望を示しました。遅延の原因は、掘削中に硬い岩盤が見つかり、機械の損傷や工事の停滞を招いたことです。中部地域道路事業管理局の副局長であるLê Văn Chung氏は、工事を加速させるために追加の機械を投入したと説明し、6月末までの完成を見込んでいます。

この道路はダラットと海沿いの町ファンティエットを結ぶ重要な路線であり、地元では改良工事の完成が待ち望まれています。雨季の到来に伴い、特にダイニン峠(đèo Đại Ninh)などの地域では、土砂崩れや道路の安全性への懸念が高まっています。地域住民は、交通の便を改善するとともに、この重要な路線を利用するすべての人の安全性と移動の利便性を高める本事業が、予定どおりに完成することを期待しています。

国道28B号の改良工事の詳細。この事業は、Bình ThuậnとLâm Đồngを結ぶ国道28B号の68km区間を改良するもので、総投資額は1兆4,000億ドン超です。工事は複数の工区に分けられており、Km21地点の区間は、Công ty TNHH xây dựng Thành Phátが施工する工区XD01に含まれます。主な情報:* 総延長:68km* 総投資額:1兆4,000億ドン超* 事業工程:当初の完成予定から遅延が発生* 主な課題:硬い岩盤の掘削、機械の損傷、土砂崩れのリスク。国道28B号の改良工事は、この地域にとって重要なインフラ事業であり、道路の安全性向上、移動時間の短縮、地域経済の発展促進が期待されています。