Dalat's Ring Road Opens but Faces Final Hurdles ## A Major Milestone for Dalat's Transportation On April 29, the Department of Construction in Lam Dong Province announced that the [Dalat Ring Road](/map/dalat-ring-road), a 7.4 km project, is set to be completed and officially opened at the start of 2026. This long-awaited infrastructure will connect key areas like Truc Lam - Yen Tu Nong (2.6 km) and An Son - Y Dinh - An Ton (4.8 km), significantly improving traffic flow in the city. However, a small but critical section of the road, over 100 meters long, remains unfinished due to two households in [Cam Ly Ward](/map/cam-ly-ward) who have yet to hand over land for construction. ## A Symbol of Progress, Yet a Local Challenge For residents of Dalat, the Ring Road has been a topic of conversation for years. It promises to ease the city’s notorious traffic congestion, especially during peak tourist seasons when streets like Pho 30/4 and Hai Ba Trung become gridlocked. Local business owners on Pho Hai Ba Trung have long awaited this development, hoping it will bring more visitors and reduce the burden on smaller roads. According to the Land Development Center in Lam Dong, the total investment for the Ring Road project has been approved at over 404 billion VND. As of now, 153 out of 157 households have received compensation and land clearance, and 155 have handed over their land. Only two households in Cam Ly Ward remain, causing the final stretch of the road to remain incomplete. ## Community Efforts and the Road Ahead Local officials have been working closely with the affected households, emphasizing the importance of the project for the city’s future. According to sources, the government is committed to resolving the issue promptly to ensure the full completion of the Ring Road. For now, the city continues to balance progress with the needs of its residents, a hallmark of Dalat’s community spirit. As the Ring Road nears completion, it stands as a testament to the city’s determination to grow while preserving its unique charm and identity. ## Dalat Ring Road Project Update The Dalat Ring Road project, spanning 7.4 km, is set to be completed and opened at the beginning of 2026. The project includes two key segments: Truc Lam - Yen Tu Nong (2.6 km) and An Son - Y Dinh - An Ton (4.8 km). Despite the overall progress, a final section of over 100 meters remains incomplete due to two households in Cam Ly Ward who have not yet handed over their land for construction. ### Key Details: - **Total investment**: Over 404 billion VND - **Completion date**: Early 2026 - **Land acquisition status**: 153 out of 157 households have received compensation, and 155 have handed over land - **Remaining issue**: Two households in Cam Ly Ward have not yet completed land handover The project is expected to significantly reduce traffic congestion in Dalat, particularly on busy roads like Hai Ba Trung and Pho 30/4. Local officials are working with the affected households to resolve the issue and ensure the full completion of the road. This infrastructure development is a key part of Dalat’s long-term transportation strategy, aiming to support both residents and the growing tourism industry. The Ring Road is also expected to improve access to key areas of the city, including popular tourist spots and local businesses. As the project nears completion, it represents a major milestone for Dalat’s development.

来源

  • Đường vành đai Đà Lạt thông xe nhưng còn 'nút thắt' 2 hộ dân — Thanh Niên

Technical Details

大叻交通建设的重要里程碑

4月29日,林同省建设厅宣布,全长7.4公里的大叻环城公路项目计划于2026年初竣工并正式通车。这项期待已久的基础设施将连接Truc Lam - Yen Tu Nong(2.6公里)和An Son - Y Dinh - An Ton(4.8公里)等重要区域,大幅改善市内交通。然而,由于Cam Ly坊有两户居民尚未移交建设用地,仍有一小段长逾100米的关键路段未能完工。

进步的象征,也是地方难题

对大叻居民而言,环城公路多年来一直是热议话题。它有望缓解这座城市长期饱受诟病的交通拥堵,尤其是在旅游旺季,Pho 30/4和Hai Ba Trung等街道常常堵得水泄不通。Pho Hai Ba Trung沿街的本地商家长期以来一直期待这条道路建成,希望它能吸引更多游客,并减轻较小道路的交通压力。

据林同省土地开发中心介绍,环城公路项目获批的总投资超过4040亿越南盾。截至目前,157户中有153户已获补偿并完成土地清场,155户已移交土地。仅剩Cam Ly坊的两户居民尚未移交土地,导致最后一段道路仍未完工。

社区的努力与未来展望

地方官员一直与受项目影响的居民密切沟通,强调该项目对城市未来的重要性。据悉,政府承诺尽快解决这一问题,确保环城公路全线完工。目前,这座城市仍在发展与居民需求之间寻求平衡,这正是大叻社区精神的体现。

随着环城公路临近竣工,它见证了这座城市在发展壮大的同时,保留自身独特魅力与特色的决心。

大叻环城公路项目进展

大叻环城公路项目全长7.4公里,计划于2026年初竣工通车。项目包含两个主要路段:Truc Lam - Yen Tu Nong(2.6公里)和An Son - Y Dinh - An Ton(4.8公里)。尽管项目整体取得进展,但由于Cam Ly坊有两户居民尚未移交建设用地,最后一段长逾100米的道路仍未完工。

关键信息:

  • 总投资:超过4040亿越南盾
  • 竣工日期:2026年初
  • 土地征收情况:157户中有153户已获补偿,155户已移交土地
  • 待解决问题:Cam Ly坊两户居民尚未完成土地移交

该项目预计将大幅缓解大叻的交通拥堵,尤其是Hai Ba Trung和Pho 30/4等繁忙道路的拥堵状况。地方官员正与受项目影响的居民沟通,以解决问题并确保道路全线完工。这项基础设施建设是大叻长期交通战略的重要组成部分,旨在服务居民并支持不断发展的旅游业。

环城公路预计还将改善前往市内重要区域的交通条件,包括热门旅游景点和本地商家所在地。随着项目临近完工,它标志着大叻发展进程中的一个重要里程碑。