历史性高速公路项目获批:芽庄—大叻高速公路计划于2030年建成

显示原文
Historic Highway Approved: Nha Trang-Đà Lạt Express Set for 2030 ## Major Transport Revolution Coming to Our Mountains A groundbreaking decision that will transform how visitors reach our beloved highland city was approved on March 30th, when Lâm Đồng Provincial People's Council passed a resolution authorizing the Nha Trang-Đà Lạt expressway project. According to Tuổi Trẻ, this ambitious 80.8-kilometer highway will cut travel time between the coastal resort of Nha Trang and our flower city to just 1.5-2 hours, nearly halving the current 3.5-4 hour journey through the winding Khánh Lê Pass on National Road 27C. ## How the Project Will Work The expressway represents a massive undertaking with a preliminary budget exceeding 25,000 billion VND. Under the approved resolution, Khánh Hòa Province will lead the project implementation using a public-private partnership (PPP) and BOT contract model. Meanwhile, Lâm Đồng will handle the local components on our territory, including land clearance compensation, resettlement support, and temporary construction work. **Our province has committed approximately 768 billion VND** from the local budget for the 2026-2030 medium-term public investment plan. ## What This Means for Đà Lạt For those of us who call Đà Lạt home, this expressway promises to be transformative. The four-lane highway with a maximum speed limit of 100km/h will directly connect our mountain plateau to the North-South Expressway Eastern route, creating unprecedented accessibility to our tourism heartland. **"This highway will link two major administrative centers while directly connecting the tourism regions of both Khánh Hòa and Lâm Đồng provinces,"** as reported by Tuổi Trẻ. ## Looking Ahead With completion targeted before 2030, this expressway represents the most significant infrastructure development for Đà Lạt in decades. For local businesses, tourism operators, and residents who frequently travel to the coast, the reduced travel time will open new possibilities for commerce and connection. The project has already received backing from the Lâm Đồng Provincial Party Committee, signaling strong political commitment to seeing this mountain-to-sea link become reality. ## Nha Trang-Đà Lạt Expressway Project Approved ### Key Project Details - **Length**: 80.8 kilometers - **Scope**: 4-lane highway - **Maximum Speed**: 100 km/h - **Total Investment**: Over 25,000 billion VND - **Target Completion**: Before 2030 - **Travel Time Reduction**: From 3.5-4 hours to 1.5-2 hours ### Implementation Structure - **Lead Authority**: Khánh Hòa Province - **Funding Model**: Public-Private Partnership (PPP) and BOT contracts - **Lâm Đồng Contribution**: 768 billion VND (2026-2030 period) ### Local Responsibilities Lâm Đồng Province will manage: - Land clearance compensation - Resettlement support programs - Temporary construction infrastructure - Local budget allocation from provincial funds ### Strategic Impact - Connects North-South Expressway Eastern route to Đà Lạt - Links two major tourism regions - Replaces current route via National Road 27C and Khánh Lê Pass - Enhances accessibility to Đà Lạt's tourism infrastructure ### Approval Timeline - March 30, 2026: Lâm Đồng Provincial People's Council approval - Previous: Lâm Đồng Provincial Party Committee endorsement - Implementation phase: 2026-2030

来源

  • Thông qua nghị quyết triển khai cao tốc Nha Trang - Đà Lạt — Tuổi Trẻ

Technical Details

我们的山城即将迎来重大交通变革

3月30日,一项将彻底改变游客前往我们这座心爱高原城市方式的里程碑式决定正式获批:林同省人民议会通过决议,批准芽庄—大叻高速公路项目。

据《青年报》(Tuổi Trẻ)报道,这条全长80.8公里、雄心勃勃的高速公路,将把沿海度假城市芽庄与我们的花城之间的行程缩短至仅需1.5至2小时,比目前经由国道27C上蜿蜒曲折的Khánh Lê山口所需的3.5至4小时,几乎缩短了一半。

项目如何推进

这条高速公路是一项规模庞大的工程,初步预算超过25万亿越盾。根据获批决议,庆和省将以公私合作(PPP)及BOT合同模式主导项目实施。

与此同时,林同省将负责本省境内的地方配套工作,包括征地补偿、搬迁安置支持及临时施工工程。本省已承诺从地方预算中投入约7,680亿越盾,纳入2026—2030年中期公共投资计划。

对大叻意味着什么

对于以大叻为家的我们来说,这条高速公路将带来深远的改变。这条最高限速100公里/小时的四车道高速公路,将把我们所在的山地高原与南北高速公路东线直接连通,为我们的旅游腹地带来前所未有的交通便利。

“这条高速公路将连接两大行政中心,同时直接连通庆和省与林同省的旅游区,”《青年报》如此报道。

展望未来

这条高速公路的目标竣工时间为2030年前,是大叻数十年来最重要的基础设施建设项目。对于本地商家、旅游运营商以及频繁往返海岸的居民而言,行程时间的缩短将为商贸往来与人员联系开辟新的可能。

该项目已获得林同省委的支持,彰显了推动这条山海通道变为现实的坚定政治决心。

芽庄—大叻高速公路项目获批

项目主要参数

  • 全长:80.8公里
  • 规模:四车道高速公路
  • 最高速度:100公里/小时
  • 总投资:超过25万亿越盾
  • 目标竣工:2030年前
  • 行程时间缩短:由3.5至4小时缩短至1.5至2小时

实施架构

  • 主导单位:庆和省
  • 融资模式:公私合作(PPP)及BOT合同
  • 林同省出资:7,680亿越盾(2026—2030年期间)

地方职责

林同省负责管理:

  • 征地补偿
  • 搬迁安置支持计划
  • 临时施工基础设施
  • 省级资金中的地方预算拨款

战略影响

  • 将南北高速公路东线与大叻连通
  • 连接两大旅游区
  • 取代经由国道27C及Khánh Lê山口的现有线路
  • 提升大叻旅游基础设施的交通可达性

审批时间线

  • 2026年3月30日:林同省人民议会批准
  • 此前:林同省委支持
  • 实施阶段:2026—2030年