New Highway 28B to Đà Lạt Nears Completion After Years of Construction
## Final Sprint Toward Completion
After years of anticipation, Đà Lạt residents and visitors may soon have a new route to our beloved mountain city. According to Thanh Niên, construction crews are racing to complete the final kilometers of National Highway 28B, particularly the challenging bridges crossing Đại Ninh Pass.
The project has reached a significant milestone, with **83% of the contract value now complete**. Lê Viết Chung, Deputy Director of the Central Road Project Management Board, reports that the highway is essentially finished from Km0 to Km68, representing approximately 914 billion of the total 1.106 trillion VND investment.
## Progress on the Mountain Approach
What's particularly encouraging for those of us who regularly navigate the winding routes to Đà Lạt is the progress on the asphalt concrete surfacing. **Nearly 60 kilometers of the 68-kilometer route now has its final road surface**, a crucial step that will determine the driving experience for countless tourists and locals.
The most technically challenging section remains the Đại Ninh Pass area, where construction teams are working intensively on the remaining bridges. Anyone who has driven the existing mountain roads knows how treacherous these passes can be, making the new infrastructure particularly welcome.
## Racing Toward April 2026 Deadline
The Central Road Project Management Board is pushing contractors to accelerate their pace to meet the **April 2026 completion target**. For Đà Lạt's tourism industry, which relies heavily on accessible transportation, this new highway could be transformational.
This alternative route promises to provide another vital connection to our mountain city, potentially easing traffic on existing roads and offering travelers a new perspective on the journey to Đà Lạt. The completion of Highway 28B will mark the end of one of the region's most significant infrastructure projects, bringing us closer to improved connectivity with the lowlands.
## Highway 28B Construction Update
### Project Status
- **Total investment**: 1.106 trillion VND
- **Current completion value**: 914 billion VND (83% complete)
- **Route completion**: Km0 to Km68 substantially finished
- **Asphalt surfacing**: 59.5 km of 68 km total completed
- **Target completion**: April 2026
### Current Focus Areas
- Final kilometers under intensive construction
- Bridge construction on Đại Ninh Pass
- Asphalt concrete surfacing completion
- Contractor acceleration efforts
### Key Details
- Project managed by Central Road Project Management Board
- Deputy Director: Lê Viết Chung
- Strategic route connecting to Đà Lạt
- Alternative transportation corridor for tourism
### Remaining Work
- 8.5 km of asphalt surfacing
- Bridge completion on mountain passes
- Final quality inspections
- Safety installations