ダラットへの新国道28B、数年の工事を経て完成間近

原文を表示
New Highway 28B to Đà Lạt Nears Completion After Years of Construction ## Final Sprint Toward Completion After years of anticipation, Đà Lạt residents and visitors may soon have a new route to our beloved mountain city. According to Thanh Niên, construction crews are racing to complete the final kilometers of National Highway 28B, particularly the challenging bridges crossing Đại Ninh Pass. The project has reached a significant milestone, with **83% of the contract value now complete**. Lê Viết Chung, Deputy Director of the Central Road Project Management Board, reports that the highway is essentially finished from Km0 to Km68, representing approximately 914 billion of the total 1.106 trillion VND investment. ## Progress on the Mountain Approach What's particularly encouraging for those of us who regularly navigate the winding routes to Đà Lạt is the progress on the asphalt concrete surfacing. **Nearly 60 kilometers of the 68-kilometer route now has its final road surface**, a crucial step that will determine the driving experience for countless tourists and locals. The most technically challenging section remains the Đại Ninh Pass area, where construction teams are working intensively on the remaining bridges. Anyone who has driven the existing mountain roads knows how treacherous these passes can be, making the new infrastructure particularly welcome. ## Racing Toward April 2026 Deadline The Central Road Project Management Board is pushing contractors to accelerate their pace to meet the **April 2026 completion target**. For Đà Lạt's tourism industry, which relies heavily on accessible transportation, this new highway could be transformational. This alternative route promises to provide another vital connection to our mountain city, potentially easing traffic on existing roads and offering travelers a new perspective on the journey to Đà Lạt. The completion of Highway 28B will mark the end of one of the region's most significant infrastructure projects, bringing us closer to improved connectivity with the lowlands. ## Highway 28B Construction Update ### Project Status - **Total investment**: 1.106 trillion VND - **Current completion value**: 914 billion VND (83% complete) - **Route completion**: Km0 to Km68 substantially finished - **Asphalt surfacing**: 59.5 km of 68 km total completed - **Target completion**: April 2026 ### Current Focus Areas - Final kilometers under intensive construction - Bridge construction on Đại Ninh Pass - Asphalt concrete surfacing completion - Contractor acceleration efforts ### Key Details - Project managed by Central Road Project Management Board - Deputy Director: Lê Viết Chung - Strategic route connecting to Đà Lạt - Alternative transportation corridor for tourism ### Remaining Work - 8.5 km of asphalt surfacing - Bridge completion on mountain passes - Final quality inspections - Safety installations

出典

  • Hiện trạng quốc lộ 28B - cung đường mới đi Đà Lạt trước ngày về đích — Thanh Niên

Technical Details

完成へのラストスパート

長年待ち望まれてきた、私たちの愛する山岳都市ダラットへの新たなルートが、まもなく住民や旅行者に開かれるかもしれません。Thanh Niênによると、工事チームは国道28Bの残り数キロメートル、特に難工事が続くĐại Ninh峠の橋梁を完成させるため、急ピッチで作業を進めています。

プロジェクトは大きな節目を迎え、契約額ベースで83%の工事が完了しました。中央道路プロジェクト管理委員会の副責任者Lê Viết Chungによると、Km0からKm68までの区間はおおむね完成しており、出来高は総投資額1兆1,060億VNDのうち約9,140億VNDに達しています。

山岳区間の進捗状況

ダラットへの曲がりくねった道を日頃から利用する私たちにとって、特に心強いのはアスファルトコンクリート舗装の進捗です。全長68キロメートルのうち、60キロメートル近くで最終仕上げの舗装が完了しました。多くの観光客や地元住民の走り心地を左右する重要な工程です。

技術的に最も難しい区間は依然としてĐại Ninh峠周辺で、工事チームは残る橋梁の建設に集中的に取り組んでいます。既存の山道を運転したことのある人なら、こうした峠道がいかに危険かを知っているでしょう。それだけに、新しいインフラの整備が歓迎されます。

2026年4月の期限に向けて工事を加速

中央道路プロジェクト管理委員会は、2026年4月の完成目標を達成するため、請負業者に工事の加速を促しています。交通アクセスに大きく依存するダラットの観光産業にとって、この新しい国道は大きな変化をもたらす可能性があります。

この代替ルートは、私たちの山岳都市への重要な接続をもう一つ提供する見込みです。既存道路の交通量を緩和し、旅行者にダラットへの道のりを新たな視点で楽しんでもらえる可能性もあります。国道28Bの完成は、この地域で最も重要なインフラプロジェクトの一つの完了を意味し、低地との交通アクセスの向上に向けた大きな一歩となります。

国道28Bの工事進捗

プロジェクトの状況

  • 総投資額: 1兆1,060億VND
  • 現在の工事出来高: 9,140億VND(83%完了)
  • 路線の完成状況: Km0からKm68までおおむね完成
  • アスファルト舗装: 全長68kmのうち59.5kmが完了
  • 完成目標: 2026年4月

現在の重点作業

  • 残り数キロメートルでの集中的な工事
  • Đại Ninh峠での橋梁建設
  • アスファルトコンクリート舗装の仕上げ
  • 請負業者による工事の加速

主な情報

  • 中央道路プロジェクト管理委員会が事業を管理
  • 副責任者: Lê Viết Chung
  • ダラットにつながる戦略的なルート
  • 観光を支える代替交通ルート

残る作業

  • 残り8.5kmのアスファルト舗装
  • 峠区間の橋梁の完成
  • 最終品質検査
  • 安全設備の設置