通往大叻的28B号新国道历经多年建设即将竣工

显示原文
New Highway 28B to Đà Lạt Nears Completion After Years of Construction ## Final Sprint Toward Completion After years of anticipation, Đà Lạt residents and visitors may soon have a new route to our beloved mountain city. According to Thanh Niên, construction crews are racing to complete the final kilometers of National Highway 28B, particularly the challenging bridges crossing Đại Ninh Pass. The project has reached a significant milestone, with **83% of the contract value now complete**. Lê Viết Chung, Deputy Director of the Central Road Project Management Board, reports that the highway is essentially finished from Km0 to Km68, representing approximately 914 billion of the total 1.106 trillion VND investment. ## Progress on the Mountain Approach What's particularly encouraging for those of us who regularly navigate the winding routes to Đà Lạt is the progress on the asphalt concrete surfacing. **Nearly 60 kilometers of the 68-kilometer route now has its final road surface**, a crucial step that will determine the driving experience for countless tourists and locals. The most technically challenging section remains the Đại Ninh Pass area, where construction teams are working intensively on the remaining bridges. Anyone who has driven the existing mountain roads knows how treacherous these passes can be, making the new infrastructure particularly welcome. ## Racing Toward April 2026 Deadline The Central Road Project Management Board is pushing contractors to accelerate their pace to meet the **April 2026 completion target**. For Đà Lạt's tourism industry, which relies heavily on accessible transportation, this new highway could be transformational. This alternative route promises to provide another vital connection to our mountain city, potentially easing traffic on existing roads and offering travelers a new perspective on the journey to Đà Lạt. The completion of Highway 28B will mark the end of one of the region's most significant infrastructure projects, bringing us closer to improved connectivity with the lowlands. ## Highway 28B Construction Update ### Project Status - **Total investment**: 1.106 trillion VND - **Current completion value**: 914 billion VND (83% complete) - **Route completion**: Km0 to Km68 substantially finished - **Asphalt surfacing**: 59.5 km of 68 km total completed - **Target completion**: April 2026 ### Current Focus Areas - Final kilometers under intensive construction - Bridge construction on Đại Ninh Pass - Asphalt concrete surfacing completion - Contractor acceleration efforts ### Key Details - Project managed by Central Road Project Management Board - Deputy Director: Lê Viết Chung - Strategic route connecting to Đà Lạt - Alternative transportation corridor for tourism ### Remaining Work - 8.5 km of asphalt surfacing - Bridge completion on mountain passes - Final quality inspections - Safety installations

来源

  • Hiện trạng quốc lộ 28B - cung đường mới đi Đà Lạt trước ngày về đích — Thanh Niên

Technical Details

竣工前的最后冲刺

经过多年的期待,大叻居民和游客或许很快就能迎来一条通往我们心爱山城的新路线。据《青年报》(Thanh Niên)报道,施工队伍正在加紧完成28B号国道最后几公里的建设,尤其是跨越Đại Ninh山口、施工难度较大的桥梁。

该项目已达到重要里程碑,目前已完成合同金额的83%。中部公路项目管理委员会副主任Lê Viết Chung表示,公路从Km0至Km68的路段已基本完工,已完成工程的价值约为9140亿越南盾,总投资为1.106万亿越南盾。

山区进城路段的建设进展

对于我们这些经常沿蜿蜒山路前往大叻的人来说,沥青混凝土路面的铺设进展尤其令人振奋。全长68公里的路线中,近60公里已完成最终路面铺设。这是至关重要的一步,将决定无数游客和当地居民的驾驶体验。

技术难度最高的路段仍在Đại Ninh山口地区,施工队正在全力推进剩余桥梁的建设。凡是驾车走过现有山路的人,都知道这些山口有多么险峻,因此人们格外期待新的基础设施。

冲刺2026年4月竣工期限

中部公路项目管理委员会正在督促承包商加快施工进度,以实现2026年4月竣工的目标。对于高度依赖便捷交通的大叻旅游业而言,这条新公路可能带来重大改变。

这条替代路线有望为我们的山城再添一条重要交通通道,缓解现有道路的交通压力,并让旅客从新的角度感受前往大叻的旅程。28B号国道竣工,将标志着该地区最重要的基础设施项目之一完工,让我们的山城与低地地区的交通联系更加便捷。

28B号国道建设进展

项目状态

  • 总投资:1.106万亿越南盾
  • 当前已完成工程价值:9140亿越南盾(完成83%)
  • 路线完工情况:Km0至Km68路段基本完工
  • 沥青路面铺设:全长68公里,已完成59.5公里
  • 目标竣工时间:2026年4月

当前重点工作

  • 加紧建设最后几公里
  • 建设Đại Ninh山口的桥梁
  • 完成沥青混凝土路面铺设
  • 推动承包商加快施工进度

关键信息

  • 项目由中部公路项目管理委员会管理
  • 副主任:Lê Viết Chung
  • 通往大叻的战略要道
  • 服务旅游业的替代交通走廊

剩余工程

  • 铺设8.5公里沥青路面
  • 完成山口桥梁建设
  • 最终质量检查
  • 安装安全设施